We will be performing a datacenter maintenance/upgrade in our Chicago location to accommodate additional growth, which will include:
1 - Power upgrade to all racks.
2 - Network equipment upgrade to all racks.
Start date: November 21 2024
End date: December 4 2024
Time of day: Off peak hours between 3PM and 3AM CST
During this 14 day window servers in Chicago will experience 1 downtime of approximately 180 minutes while power and network in that specific rack is upgraded.
Servers that are currently being affected by the maintenance will show message "Node is currently locked" in your dashboard.