Cloudfanatic - Chicago datacenter maintenance/upgrade – Maintenance details
All systems operational
Chicago datacenter maintenance/upgrade
Completed
Scheduled for November 21, 2024 at 2:50 PM – November 29, 2024 at 12:42 AM
Affects
Chicago Datacenter - USA Central
Under maintenance from 2:50 PM to 12:42 AM
Legacy Container (*VZ) services
Under maintenance from 2:50 PM to 12:42 AM
Network
Under maintenance from 2:50 PM to 12:42 AM
10Gbps Cloud servers
Under maintenance from 2:50 PM to 12:42 AM
Virtual and Hybrid servers
Under maintenance from 2:50 PM to 12:42 AM
Updates
Completed
November 29, 2024 at 12:42 AM
Completed
November 29, 2024 at 12:42 AM
Maintenance has now been completed ahead of schedule.
In progress
November 21, 2024 at 2:50 PM
In progress
November 21, 2024 at 2:50 PM
We will be performing a datacenter maintenance/upgrade in our Chicago location to accommodate additional growth, which will include:
1 - Power upgrade to all racks. 2 - Network equipment upgrade to all racks.
Start date: November 21 2024 End date: December 4 2024 Time of day: Off peak hours between 3PM and 3AM CST
During this 14 day window servers in Chicago will experience 1 downtime of approximately 180 minutes while power and network in that specific rack is upgraded. Servers that are currently being affected by the maintenance will show message "Node is currently locked" in your dashboard.